GOLDEN DIGITAL GATEWAY

“Data centres are actually being built next to where the power is because power is such an important consideration”

Nicholas Toh, Managing Director – Head of Data
Centre Platform, Asia( Ex-China), Gaw Capital Partners train units, where the UPS and all the different components are connected.”
Factory testing eliminates uncertainty about system functionality during commissioning.“ This ensures that everything works coming out of the factory, which reduces a lot of our construction risk. If things don’ t work and can’ t be commissioned on-site, there’ ll be a major issue with our timeline,” says Kah Jin.
Beyond power systems, the facility’ s connectivity strategy required partnerships with multiple fibre providers. Kah Jin describes these